Sage

76MWdc solar facility located in Rich County, Utah

Sage is a 58MWac solar PV system located in Rich County, Utah. Sage began construction in August 2018 and commenced operations in September 2019.

Implementation of the project included the installation of approximately 636,000 thin film First Solar PV solar panels on framed steel pole support structures, associated electrical equipment, a substation and an operation and maintenance (O&M) building.

The project was tax equity financed by Wells Fargo. Ingka Holdings acquired a 49% stake of the project in 2019.